| Project: | CS1 L8 P-1609 |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 107 | Shower doors and mirrors | 12/01/09 | 3d | 12/03/09 | 66.67% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 12/08/09 | |
| 91 | landscaping | 12/03/09 | 3d | 12/08/09 | 0% |
| 110 | 1.12 Complete final inspection for certificate of occupancy | 12/03/09 | 1d | 12/03/09 | 0% |
| 112 | Cleanup for occupancy | 12/04/09 | 16h | 12/07/09 | 0% |
| 122 | Draw #5 - 10% | 12/04/09 | 0.5h | 12/04/09 | 0% |
| 113 | TOUCH UP PAINT | 12/08/09 | 1h | 12/08/09 | 0% |
| 114 | Perform final walk-through inspection | 12/08/09 | 1h | 12/08/09 | 0% |
| 115 | Complete punch list items | 12/08/09 | 1h | 12/08/09 | 0% |
| 123 | Closing | 12/08/09 | 1h | 12/08/09 | 0% |
|