| Project: | LR1 L128 P-1609 |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 18 | order Floor Tile | 09/30/09 | 0w | 10/13/09 | 0% |
| 101 | landscaping | 11/18/09 | 5d | 12/10/09 | 20% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 12/15/09 | |
| 119 | Carpet 1st floor | 12/04/09 | 8h | 12/04/09 | 0% |
| 122 | Cleanup for occupancy | 12/04/09 | 8h | 12/04/09 | 0% |
| 112 | locks,stops screens,etc.appliances,etc. | 12/07/09 | 6h | 12/07/09 | 0% |
| 123 | TOUCH UP PAINT | 12/07/09 | 4d | 12/10/09 | 0% |
| 21 | Gate mfg. Long Lead | 12/09/09 | 16h | 12/10/09 | 0% |
| 124 | Perform final walk-through inspection | 12/11/09 | 1d | 12/11/09 | 0% |
| 125 | Complete punch list items | 12/14/09 | 1h | 12/14/09 | 0% |
| 133 | owner for closing | 12/14/09 | 1d | 12/15/09 | 0% |
|