|

| | | | | | | | | | | |
| Project: | LR1 L95 P-1609 |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 14 | order appliances | 10/14/09 | 2w | 12/07/09 | 72.75% |
| 28 | Rough-in underground plumbing, sewer & other | 09/02/09 | 0h | 09/03/09 | 0% |
| 31 | Backfill Plumbing | 09/04/09 | 0h | 09/04/09 | 0% |
| 100 | Install Roof Tile | 12/01/09 | 4d | 12/08/09 | 50% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 12/18/09 | |
| 99 | Color Coat exterior | 12/03/09 | 16h | 12/04/09 | 0% |
| 121 | mirrors SHWR DOOR | 12/04/09 | 3d | 12/08/09 | 0% |
| 102 | Install fence | 12/07/09 | 48h | 12/14/09 | 0% |
| 108 | Finalize Electrical | 12/07/09 | 8h | 12/07/09 | 0% |
| 109 | Install Light Fixtures (In & Out) | 12/07/09 | 3d | 12/09/09 | 0% |
| 112 | Complete 1st floor - zone 1 HVAC | 12/07/09 | 8h | 12/07/09 | 0% |
| 116 | deliver appliances | 12/07/09 | 3h | 12/08/09 | 0% |
| 110 | communications TRIM - phone, cable | 12/08/09 | 8h | 12/08/09 | 0% |
| 113 | start check hvac | 12/08/09 | 2h | 12/08/09 | 0% |
| 117 | Install Stove, Dishwaster, etc | 12/08/09 | 4h | 12/08/09 | 0% |
| 124 | 1.12 Complete final inspection for certificate of occupancy | 12/10/09 | 1d | 12/10/09 | 0% |
| 104 | landscaping | 12/11/09 | 3d | 12/15/09 | 0% |
| 126 | Cleanup for occupancy | 12/11/09 | 8h | 12/11/09 | 0% |
| 136 | Draw #5 - 10% | 12/11/09 | 0.5h | 12/11/09 | 0% |
| 127 | TOUCH UP PAINT | 12/14/09 | 1d | 12/14/09 | 0% |
| 22 | Gate mfg. Long Lead | 12/15/09 | 16h | 12/16/09 | 0% |
| 103 | INSTALL GATE | 12/15/09 | 2d | 12/16/09 | 0% |
|