Home > Customer Progress > Uncompleted Projects > Last Updated: 12/02/09

Project:LR1 L95 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
14order appliances 10/14/092w12/07/0972.75%
28Rough-in underground plumbing, sewer & other09/02/090h09/03/090%
31Backfill Plumbing09/04/090h09/04/090%
100Install Roof Tile 12/01/094d12/08/0950%
Task(s) Scheduled to Start in Between 12/02/09and12/18/09
99Color Coat exterior12/03/0916h12/04/090%
121 mirrors SHWR DOOR12/04/093d12/08/090%
102Install fence12/07/0948h12/14/090%
108Finalize Electrical12/07/098h12/07/090%
109Install Light Fixtures (In & Out)12/07/093d12/09/090%
112Complete 1st floor - zone 1 HVAC12/07/098h12/07/090%
116deliver appliances12/07/093h12/08/090%
110communications TRIM - phone, cable12/08/098h12/08/090%
113start check hvac12/08/092h12/08/090%
117Install Stove, Dishwaster, etc12/08/094h12/08/090%
1241.12 Complete final inspection for certificate of occupancy12/10/091d12/10/090%
104landscaping12/11/093d12/15/090%
126Cleanup for occupancy12/11/098h12/11/090%
136Draw #5 - 10%12/11/090.5h12/11/090%
127TOUCH UP PAINT12/14/091d12/14/090%
22Gate mfg. Long Lead12/15/0916h12/16/090%
103INSTALL GATE12/15/092d12/16/090%