| Project: | LR1 L239 P-1764-A |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 7 | roof tile (LIVINGSTON) #4576 FLAT | 11/18/09 | 6w | 12/30/09 | 32.92% |
| 8 | FRNT DR. | 11/18/09 | 7w | 01/06/10 | 28.21% |
| 9 | prefab wall mfg. PLAN-1764 A | 11/18/09 | 2w | 12/02/09 | 98.75% |
| 11 | Truss mfg.PLAN-1764 A | 11/18/09 | 2w | 12/02/09 | 98.75% |
| 12 | Windows mfg.TAN LOW E NO GRIDS | 11/18/09 | 112h | 12/08/09 | 70.54% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 03/30/10 | |
| 31 | Backfill Plumbing | 12/02/09 | 4h | 12/02/09 | 0% |
| 33 | Final Excavate & Prep for foundations | 12/02/09 | 2d | 12/04/09 | 0% |
| 34 | INSTALL POST TENSION CABLES | 12/07/09 | 1d | 12/07/09 | 0% |
| 35 | 1.4 Inspection on Footings | 12/08/09 | 1d | 12/08/09 | 0% |
| 36 | Termite Pre-treat | 12/09/09 | 1.5h | 12/09/09 | 0% |
| 37 | Pour concrete for foundations & slabs | 12/09/09 | 1d | 12/10/09 | 0% |
| 38 | Strip foundation forms, GRADE & CURE | 12/10/09 | 1d | 12/11/09 | 0% |
| 41 | Snap Lines stand walls | 12/11/09 | 2d | 12/15/09 | 0% |
| 132 | Draw #1 - 20% | 12/14/09 | 0.5h | 12/14/09 | 0% |
| 42 | Plumb in Line - 1st Floor | 12/15/09 | 1d | 12/16/09 | 0% |