Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:CS1 L1 4341 w. linda lane P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
123Closing10/19/09278h12/04/0994.24%
Task(s) Scheduled to Start in Between 12/02/09and12/04/09
All TasksFinished DatePercent Completed
4341 w linda lane AVILA P-160912/02/0998.3%
  Color Chart Completed (Notice to Proceed)05/11/09100%
  Long Lead Items10/12/09100%
    new owner09/21/09100%
    Temporary Power /BLUE STAKE05/14/09100%
    roof SHINGLE production 06/01/09100%
    Exterior Door mfg.05/18/09100%
    FRAMING NOTIFICATION PLAN 1609 w/ patio05/25/09100%
    Truss mfg. PLAN 1609w/ porch and patio05/25/09100%
    Windows mfg.05/11/09100%
    order appliances 10/06/09100%
     cabinet Long Lead07/01/09100%
     VANITIY countertop (mfg) long lead09/15/09100%
    order Floor Tile 09/30/09100%
    formica09/09/09100%
     order Carpet10/12/09100%
    Fencing long Lead07/03/09100%
    Gate mfg. Long Lead07/13/09100%
  Site Work plus05/21/09100%
    Secure Permits05/14/09100%
    Build up House Pad05/19/09100%
    call BLUE STAKE05/11/09100%
    Set Forms05/18/09100%
    Rough-in underground plumbing, sewer & other05/18/09100%
    Install temporary power service05/19/09100%
    1.3 Inspect Plumbing Under/temp pwr05/20/09100%
    Backfill Plumbing05/21/09100%
  Foundation05/29/09100%
    Final Excavate & Prep for foundations05/22/09100%
    1.4 Inspection on Footings05/25/09100%
    Termite Pre-treat05/25/09100%
    Pour concrete for foundations & slabs05/27/09100%
    Strip foundation forms, GRADE & CURE05/28/09100%
    GRADE & Cure foundation05/29/09100%
    POUR PATIO/PORCH05/29/09100%
  Framing06/08/09100%
    Deliver LUMBER and trusses05/29/09100%
    Snap Lines stand walls06/01/09100%
    Complete roof framing (trusses & Sheeting)06/04/09100%
    INSPECTION ROOF NAILING06/04/09100%
    complete interior framing06/05/09100%
    INSPECTION SHEAR NAILING06/05/09100%
    rough clean up06/08/09100%
    Install Windows06/08/09100%
  Utility Rough-Ins06/11/09100%
    HVAC Calcs & layout06/08/09100%
    Rough-in HVAC06/11/09100%
    Rough-in Plumbing06/08/09100%
    Rough-in electrical06/09/09100%
    Rough-in phone, cable06/08/09100%
    rough clean up06/09/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.06/11/09100%
  Dry In06/12/09100%
    Install felt, flashing,HOT MOP06/12/09100%
  STUCCO &LATH06/17/09100%
    Complete Lathing06/15/09100%
    1.9.2 Inspect Drywall/lathing06/17/09100%
  Interior Finishes10/08/09100%
    Insulation06/17/09100%
      Place wall insulation06/16/09100%
      Place ceiling insulation06/17/09100%
    Drywall06/24/09100%
      Install drywall - 1st floor overhead06/16/09100%
      1.9.2 Inspect Drywall/lathing06/17/09100%
      Tape and float 1st floor drywall06/22/09100%
      Texture AND CLEAN UP06/24/09100%
    Trim Carpentry09/23/09100%
      install front door06/30/09100%
      DOORS,BASE,SHELVING09/23/09100%
    Paint 09/03/09100%
      Exterior Trim Paint06/18/09100%
      prep &Paint09/03/09100%
    Cabinets & woodwork09/09/09100%
      Cabinet Bases 09/07/09100%
      Cabinet Scribe mold & uppers09/08/09100%
      base in fil & front door lock09/09/09100%
    Countertops09/10/09100%
      formica tops09/10/09100%
     Tile installation10/08/09100%
      Standard tile EXCEPT BEDROOMS10/08/09100%
  EXTERIOR FINISHES10/16/09100%
    Complete brown coat06/17/09100%
    Rough Grade07/06/09100%
    Pour concrete driveway and sidewalks07/23/09100%
    Color Coat exterior09/22/09100%
    Install garage door09/23/09100%
    Install fence07/09/09100%
    Install Gate09/21/09100%
    landscaping10/16/09100%
  FINAL TRIMS10/14/09100%
    Finish Electrical10/08/09100%
      Complete 1st floor circuits to service panel09/28/09100%
      Finalize Electrical10/08/09100%
    Install Light Fixtures (In & Out)10/12/09100%
    communications TRIM - phone, cable10/09/09100%
    Finish HVAC10/12/09100%
      Complete 1st floor - zone 1 HVAC09/30/09100%
      start check hvac10/12/09100%
    Final Trim10/14/09100%
      locks,stops screens,etc.appliances,etc.10/14/09100%
      deliver appliances10/07/09100%
      Install Stove, Dishwaster, etc10/08/09100%
    Finish Plumbing10/09/09100%
      Install all Plumbing Fixtures10/09/09100%
    Shower doors and mirrors10/13/09100%
    Carpet10/13/09100%
      Carpet 1st floor10/13/09100%
  1.12 Complete final inspection for certificate of occupancy10/13/09100%
  Final Acceptance10/19/09100%
    Cleanup for occupancy10/15/09100%
    TOUCH UP PAINT10/16/09100%
    Perform final walk-through inspection10/19/09100%
    Complete punch list items10/19/09100%
  Loan & Draw Schedule12/02/0994.32%
    Set up Loan05/14/09100%
    Draw #1 - 20%05/25/09100%
    Draw #2 - 25%06/04/09100%
    Draw #3 - 25%06/12/09100%
    Draw #4 - 20%09/04/09100%
    Draw #5 - 10%10/14/09100%
    Closing12/02/0994.24%