Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:CS1 L50 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
123Closing11/04/09182h12/04/0991.21%
Task(s) Scheduled to Start in Between 12/02/09and12/04/09
All TasksFinished DatePercent Completed
486 S 45TH DR NAME HERE P-160912/02/0997.26%
  Color Chart Completed (Notice to Proceed)08/20/09100%
  Long Lead Items10/21/09100%
    new owner08/25/09100%
    Temporary Power /BLUE STAKE08/25/09100%
    roof SHINGLE production 09/10/09100%
    Exterior Door mfg.08/27/09100%
    FRAMING NOTIFICATION PLAN 1609 NO PATIO09/03/09100%
    Truss mfg. PLAN 1609w/ porch NO PATIO09/03/09100%
    Windows mfg.08/20/09100%
    order appliances 10/08/09100%
     cabinet Long Lead10/12/09100%
     VANITIY countertop (mfg) long lead10/13/09100%
    order Floor Tile 10/09/09100%
    formica10/13/09100%
     order Carpet08/27/09100%
    Fencing long Lead10/12/09100%
    Gate mfg. Long Lead10/21/09100%
  Site Work plus08/28/09100%
    Secure Permits08/25/09100%
    Build up House Pad08/28/09100%
    call BLUE STAKE08/20/09100%
    Set Forms08/24/09100%
    Rough-in underground plumbing, sewer & other08/25/09100%
    Install temporary power service08/26/09100%
    1.3 Inspect Plumbing Under/temp pwr08/27/09100%
    Backfill Plumbing08/28/09100%
  Foundation09/11/09100%
    Final Excavate & Prep for foundations09/04/09100%
    1.4 Inspection on Footings09/08/09100%
    Termite Pre-treat09/09/09100%
    Pour concrete for foundations & slabs09/10/09100%
    Strip foundation forms, GRADE & CURE09/10/09100%
    GRADE & Cure foundation09/11/09100%
    POUR PATIO/PORCH09/11/09100%
  Framing09/21/09100%
    Deliver LUMBER and trusses09/11/09100%
    Snap Lines stand walls09/14/09100%
    Complete roof framing (trusses & Sheeting)09/17/09100%
    INSPECTION ROOF NAILING09/18/09100%
    complete interior framing09/18/09100%
    INSPECTION SHEAR NAILING09/21/09100%
    rough clean up09/21/09100%
    Install Windows09/21/09100%
  Utility Rough-Ins09/24/09100%
    HVAC Calcs & layout09/18/09100%
    Rough-in HVAC09/22/09100%
    Rough-in Plumbing09/22/09100%
    Rough-in electrical09/24/09100%
    Rough-in phone, cable09/23/09100%
    rough clean up09/23/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.09/24/09100%
  Dry In09/22/09100%
    Install felt, flashing,HOT MOP09/22/09100%
  STUCCO &LATH09/29/09100%
    Complete Lathing09/24/09100%
    1.9.2 Inspect Drywall/lathing09/29/09100%
  Interior Finishes10/14/09100%
    Insulation09/28/09100%
      Place wall insulation09/25/09100%
      Place ceiling insulation09/28/09100%
    Drywall10/02/09100%
      Install drywall - 1st floor overhead09/29/09100%
      1.9.2 Inspect Drywall/lathing09/29/09100%
      Tape and float 1st floor drywall10/02/09100%
      Texture AND CLEAN UP10/02/09100%
    Trim Carpentry10/06/09100%
      install front door10/06/09100%
      DOORS,BASE,SHELVING10/06/09100%
    Paint 10/08/09100%
      Exterior Trim Paint10/02/09100%
      prep &Paint10/08/09100%
    Cabinets & woodwork10/12/09100%
      Cabinet Bases 10/09/09100%
      Cabinet Scribe mold & uppers10/12/09100%
      base in fil & front door lock10/12/09100%
    Countertops10/14/09100%
      formica tops10/14/09100%
     Tile installation10/14/09100%
      Standard tile EXCEPT BEDROOMS10/14/09100%
  EXTERIOR FINISHES10/22/09100%
    Complete brown coat10/01/09100%
    Rough Grade10/02/09100%
    Pour concrete driveway and sidewalks10/08/09100%
    Color Coat exterior10/19/09100%
    Install garage door10/19/09100%
    Install fence10/19/09100%
    Install Gate10/22/09100%
    landscaping10/22/09100%
  FINAL TRIMS10/26/09100%
    Finish Electrical10/20/09100%
      Complete 1st floor circuits to service panel10/19/09100%
      Finalize Electrical10/20/09100%
    Install Light Fixtures (In & Out)10/26/09100%
    communications TRIM - phone, cable10/21/09100%
    Finish HVAC10/21/09100%
      Complete 1st floor - zone 1 HVAC10/13/09100%
      start check hvac10/21/09100%
    Final Trim10/21/09100%
      locks,stops screens,etc.appliances,etc.10/21/09100%
      deliver appliances10/15/09100%
      Install Stove, Dishwaster, etc10/20/09100%
    Finish Plumbing10/15/09100%
      Install all Plumbing Fixtures10/15/09100%
    Shower doors and mirrors10/20/09100%
    Carpet10/20/09100%
      Carpet 1st floor10/20/09100%
  1.12 Complete final inspection for certificate of occupancy10/26/09100%
  Final Acceptance11/05/09100%
    Cleanup for occupancy11/03/09100%
    TOUCH UP PAINT11/05/09100%
    Perform final walk-through inspection11/04/09100%
    Complete punch list items11/04/09100%
  Loan & Draw Schedule12/02/0991.37%
    Set up Loan08/25/09100%
    Draw #1 - 20%09/09/09100%
    Draw #2 - 25%09/17/09100%
    Draw #3 - 25%09/25/09100%
    Draw #4 - 20%10/08/09100%
    Draw #5 - 10%10/27/09100%
    Closing12/02/0991.21%