| Project: | CS1 L50 P-1609 |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 123 | Closing | 11/04/09 | 182h | 12/04/09 | 91.21% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 12/04/09 | |
|
| All Tasks | Finished Date | Percent Completed |
| 486 S 45TH DR NAME HERE P-1609 | 12/02/09 | 97.26% |
| Color Chart Completed (Notice to Proceed) | 08/20/09 | 100% |
| Long Lead Items | 10/21/09 | 100% |
| new owner | 08/25/09 | 100% |
| Temporary Power /BLUE STAKE | 08/25/09 | 100% |
| roof SHINGLE production | 09/10/09 | 100% |
| Exterior Door mfg. | 08/27/09 | 100% |
| FRAMING NOTIFICATION PLAN 1609 NO PATIO | 09/03/09 | 100% |
| Truss mfg. PLAN 1609w/ porch NO PATIO | 09/03/09 | 100% |
| Windows mfg. | 08/20/09 | 100% |
| order appliances | 10/08/09 | 100% |
| cabinet Long Lead | 10/12/09 | 100% |
| VANITIY countertop (mfg) long lead | 10/13/09 | 100% |
| order Floor Tile | 10/09/09 | 100% |
| formica | 10/13/09 | 100% |
| order Carpet | 08/27/09 | 100% |
| Fencing long Lead | 10/12/09 | 100% |
| Gate mfg. Long Lead | 10/21/09 | 100% |
| Site Work plus | 08/28/09 | 100% |
| Secure Permits | 08/25/09 | 100% |
| Build up House Pad | 08/28/09 | 100% |
| call BLUE STAKE | 08/20/09 | 100% |
| Set Forms | 08/24/09 | 100% |
| Rough-in underground plumbing, sewer & other | 08/25/09 | 100% |
| Install temporary power service | 08/26/09 | 100% |
| 1.3 Inspect Plumbing Under/temp pwr | 08/27/09 | 100% |
| Backfill Plumbing | 08/28/09 | 100% |
| Foundation | 09/11/09 | 100% |
| Final Excavate & Prep for foundations | 09/04/09 | 100% |
| 1.4 Inspection on Footings | 09/08/09 | 100% |
| Termite Pre-treat | 09/09/09 | 100% |
| Pour concrete for foundations & slabs | 09/10/09 | 100% |
| Strip foundation forms, GRADE & CURE | 09/10/09 | 100% |
| GRADE & Cure foundation | 09/11/09 | 100% |
| POUR PATIO/PORCH | 09/11/09 | 100% |
| Framing | 09/21/09 | 100% |
| Deliver LUMBER and trusses | 09/11/09 | 100% |
| Snap Lines stand walls | 09/14/09 | 100% |
| Complete roof framing (trusses & Sheeting) | 09/17/09 | 100% |
| INSPECTION ROOF NAILING | 09/18/09 | 100% |
| complete interior framing | 09/18/09 | 100% |
| INSPECTION SHEAR NAILING | 09/21/09 | 100% |
| rough clean up | 09/21/09 | 100% |
| Install Windows | 09/21/09 | 100% |
| Utility Rough-Ins | 09/24/09 | 100% |
| HVAC Calcs & layout | 09/18/09 | 100% |
| Rough-in HVAC | 09/22/09 | 100% |
| Rough-in Plumbing | 09/22/09 | 100% |
| Rough-in electrical | 09/24/09 | 100% |
| Rough-in phone, cable | 09/23/09 | 100% |
| rough clean up | 09/23/09 | 100% |
| 1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc. | 09/24/09 | 100% |
| Dry In | 09/22/09 | 100% |
| Install felt, flashing,HOT MOP | 09/22/09 | 100% |
| STUCCO &LATH | 09/29/09 | 100% |
| Complete Lathing | 09/24/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 09/29/09 | 100% |
| Interior Finishes | 10/14/09 | 100% |
| Insulation | 09/28/09 | 100% |
| Place wall insulation | 09/25/09 | 100% |
| Place ceiling insulation | 09/28/09 | 100% |
| Drywall | 10/02/09 | 100% |
| Install drywall - 1st floor overhead | 09/29/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 09/29/09 | 100% |
| Tape and float 1st floor drywall | 10/02/09 | 100% |
| Texture AND CLEAN UP | 10/02/09 | 100% |
| Trim Carpentry | 10/06/09 | 100% |
| install front door | 10/06/09 | 100% |
| DOORS,BASE,SHELVING | 10/06/09 | 100% |
| Paint | 10/08/09 | 100% |
| Exterior Trim Paint | 10/02/09 | 100% |
| prep &Paint | 10/08/09 | 100% |
| Cabinets & woodwork | 10/12/09 | 100% |
| Cabinet Bases | 10/09/09 | 100% |
| Cabinet Scribe mold & uppers | 10/12/09 | 100% |
| base in fil & front door lock | 10/12/09 | 100% |
| Countertops | 10/14/09 | 100% |
| formica tops | 10/14/09 | 100% |
| Tile installation | 10/14/09 | 100% |
| Standard tile EXCEPT BEDROOMS | 10/14/09 | 100% |
| EXTERIOR FINISHES | 10/22/09 | 100% |
| Complete brown coat | 10/01/09 | 100% |
| Rough Grade | 10/02/09 | 100% |
| Pour concrete driveway and sidewalks | 10/08/09 | 100% |
| Color Coat exterior | 10/19/09 | 100% |
| Install garage door | 10/19/09 | 100% |
| Install fence | 10/19/09 | 100% |
| Install Gate | 10/22/09 | 100% |
| landscaping | 10/22/09 | 100% |
| FINAL TRIMS | 10/26/09 | 100% |
| Finish Electrical | 10/20/09 | 100% |
| Complete 1st floor circuits to service panel | 10/19/09 | 100% |
| Finalize Electrical | 10/20/09 | 100% |
| Install Light Fixtures (In & Out) | 10/26/09 | 100% |
| communications TRIM - phone, cable | 10/21/09 | 100% |
| Finish HVAC | 10/21/09 | 100% |
| Complete 1st floor - zone 1 HVAC | 10/13/09 | 100% |
| start check hvac | 10/21/09 | 100% |
| Final Trim | 10/21/09 | 100% |
| locks,stops screens,etc.appliances,etc. | 10/21/09 | 100% |
| deliver appliances | 10/15/09 | 100% |
| Install Stove, Dishwaster, etc | 10/20/09 | 100% |
| Finish Plumbing | 10/15/09 | 100% |
| Install all Plumbing Fixtures | 10/15/09 | 100% |
| Shower doors and mirrors | 10/20/09 | 100% |
| Carpet | 10/20/09 | 100% |
| Carpet 1st floor | 10/20/09 | 100% |
| 1.12 Complete final inspection for certificate of occupancy | 10/26/09 | 100% |
| Final Acceptance | 11/05/09 | 100% |
| Cleanup for occupancy | 11/03/09 | 100% |
| TOUCH UP PAINT | 11/05/09 | 100% |
| Perform final walk-through inspection | 11/04/09 | 100% |
| Complete punch list items | 11/04/09 | 100% |
| Loan & Draw Schedule | 12/02/09 | 91.37% |
| Set up Loan | 08/25/09 | 100% |
| Draw #1 - 20% | 09/09/09 | 100% |
| Draw #2 - 25% | 09/17/09 | 100% |
| Draw #3 - 25% | 09/25/09 | 100% |
| Draw #4 - 20% | 10/08/09 | 100% |
| Draw #5 - 10% | 10/27/09 | 100% |
| Closing | 12/02/09 | 91.21% |