Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:CS1 L8 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
107Shower doors and mirrors12/01/093d12/03/0966.67%
Task(s) Scheduled to Start in Between 12/02/09and12/08/09
91landscaping12/03/093d12/08/090%
1101.12 Complete final inspection for certificate of occupancy12/03/091d12/03/090%
112Cleanup for occupancy12/04/0916h12/07/090%
122Draw #5 - 10%12/04/090.5h12/04/090%
113TOUCH UP PAINT12/08/091h12/08/090%
114Perform final walk-through inspection12/08/091h12/08/090%
115Complete punch list items12/08/091h12/08/090%
123Closing12/08/091h12/08/090%
All TasksFinished DatePercent Completed
546 S 46 TH AVEP- 1609 ROSALES 12/02/0992.9%
  Color Chart Completed (Notice to Proceed)09/24/09100%
  Long Lead Items11/20/09100%
    new owner09/24/09100%
    Temporary Power /BLUE STAKE09/29/09100%
    roof SHINGLE production 10/15/09100%
    Exterior Door mfg.10/01/09100%
    FRAMING NOTIFICATION PLAN 1609 NO PATIO10/08/09100%
    Truss mfg. PLAN 1609w/ porch NO PATIO10/08/09100%
    Windows mfg.09/24/09100%
    order appliances 11/17/09100%
     cabinet Long Lead11/04/09100%
     VANITIY countertop (mfg) long lead11/18/09100%
    order Floor Tile 11/12/09100%
    formica11/18/09100%
     order Carpet11/20/09100%
    Fencing long Lead11/09/09100%
    Gate mfg. Long Lead11/18/09100%
  Site Work plus10/01/09100%
    Secure Permits09/25/09100%
    Build up House Pad09/29/09100%
    call BLUE STAKE09/24/09100%
    Set Forms09/30/09100%
    Rough-in underground plumbing, sewer & other09/25/09100%
    Install temporary power service10/01/09100%
    1.3 Inspect Plumbing Under/temp pwr09/28/09100%
    Backfill Plumbing09/29/09100%
  Foundation10/06/09100%
    Final Excavate & Prep for foundations10/02/09100%
    1.4 Inspection on Footings10/01/09100%
    Termite Pre-treat10/02/09100%
    Pour concrete for foundations & slabs10/05/09100%
    Strip foundation forms, GRADE & CURE10/05/09100%
    GRADE & Cure foundation10/06/09100%
  Framing10/16/09100%
    Deliver LUMBER and trusses10/08/09100%
    Snap Lines stand walls10/09/09100%
    Complete roof framing (trusses & Sheeting)10/14/09100%
    INSPECTION ROOF NAILING10/14/09100%
    complete interior framing10/15/09100%
    INSPECTION SHEAR NAILING10/15/09100%
    rough clean up10/16/09100%
    Install Windows10/16/09100%
  Utility Rough-Ins10/21/09100%
    HVAC Calcs & layout10/15/09100%
    Rough-in HVAC10/16/09100%
    Rough-in Plumbing10/19/09100%
    Rough-in electrical10/20/09100%
    Rough-in phone, cable10/21/09100%
    rough clean up10/21/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.10/21/09100%
  Dry In10/20/09100%
    Install felt, flashing,HOT MOP10/20/09100%
  STUCCO &LATH10/26/09100%
    Complete Lathing10/21/09100%
    1.9.2 Inspect Drywall/lathing10/26/09100%
  Interior Finishes11/17/09100%
    Insulation10/22/09100%
      Place wall insulation10/22/09100%
      Place ceiling insulation10/22/09100%
    Drywall11/03/09100%
      Install drywall - 1st floor overhead10/23/09100%
      1.9.2 Inspect Drywall/lathing10/26/09100%
      Tape and float 1st floor drywall10/29/09100%
      Texture AND CLEAN UP11/03/09100%
    Trim Carpentry11/05/09100%
      install front door11/04/09100%
      DOORS,BASE,SHELVING11/05/09100%
    Paint 11/06/09100%
      Exterior Trim Paint10/27/09100%
      prep &Paint11/06/09100%
    Cabinets & woodwork11/11/09100%
      Cabinet Bases 11/10/09100%
      Cabinet Scribe mold & uppers11/11/09100%
      base in fil & front door lock11/11/09100%
    Countertops11/16/09100%
      formica tops11/16/09100%
     Tile installation11/17/09100%
      Standard tile EXCEPT BEDROOMS11/17/09100%
  EXTERIOR FINISHES11/19/0977.78%
    Complete brown coat10/26/09100%
    Rough Grade11/04/09100%
    Pour concrete driveway and sidewalks11/09/09100%
    Color Coat exterior11/16/09100%
    Install garage door11/19/09100%
    Install fence11/13/09100%
    Install Gate11/19/09100%
    landscaping0%
  FINAL TRIMS12/02/0988.06%
    Finish Electrical11/23/09100%
      Complete 1st floor circuits to service panel11/20/09100%
      Finalize Electrical11/23/09100%
    Install Light Fixtures (In & Out)11/23/09100%
    communications TRIM - phone, cable11/24/09100%
    Finish HVAC11/24/09100%
      Complete 1st floor - zone 1 HVAC11/23/09100%
      start check hvac11/24/09100%
    Final Trim11/24/09100%
      locks,stops screens,etc.appliances,etc.11/24/09100%
      deliver appliances11/17/09100%
      Install Stove, Dishwaster, etc11/23/09100%
    Finish Plumbing11/18/09100%
      Install all Plumbing Fixtures11/18/09100%
    Shower doors and mirrors12/02/0966.67%
    Carpet11/23/09100%
      Carpet 1st floor11/23/09100%
  1.12 Complete final inspection for certificate of occupancy0%
  Final Acceptance0%
    Cleanup for occupancy0%
    TOUCH UP PAINT0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule11/06/0966.67%
    Set up Loan09/25/09100%
    Draw #1 - 20%10/02/09100%
    Draw #2 - 25%10/14/09100%
    Draw #3 - 25%10/22/09100%
    Draw #4 - 20%11/06/09100%
    Draw #5 - 10%0%
    Closing0%