Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:LR1 L128 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
18order Floor Tile 09/30/090w10/13/090%
101landscaping11/18/095d12/10/0920%
Task(s) Scheduled to Start in Between 12/02/09and12/15/09
119Carpet 1st floor12/04/098h12/04/090%
122Cleanup for occupancy12/04/098h12/04/090%
112locks,stops screens,etc.appliances,etc.12/07/096h12/07/090%
123TOUCH UP PAINT12/07/094d12/10/090%
21Gate mfg. Long Lead12/09/0916h12/10/090%
124Perform final walk-through inspection12/11/091d12/11/090%
125Complete punch list items12/14/091h12/14/090%
133owner for closing12/14/091d12/15/090%
All TasksFinished DatePercent Completed
3684 S. 39TH DR SPEC11/20/0988.4%
  Sign contract08/14/09100%
  Color Chart Completed (Notice to Proceed)08/14/09100%
  Long Lead Items11/06/0996.71%
    power meter long lead08/21/09100%
    Temporary Power /BLUE STAKE08/19/09100%
    roof tile (LIVINGSTON) #3578 S TILE09/25/09100%
    FRNT DR.10/02/09100%
    prefab wall mfg. PLAN-1609 W/ PATIO08/28/09100%
    post tension notification PLAN-160908/24/09100%
    Truss mfg.PLAN-160908/28/09100%
    Windows mfg. WHITE NO GRIDSLOW E09/03/09100%
    order appliances 11/06/09100%
     Cabinet Long Lead & Construction10/09/09100%
     1 marble countertop (mfg) long lead/ formica kit10/30/09100%
    order VANITY/shower Tile (see specs)10/15/09100%
    order Floor Tile 10/13/090%
     order Carpet 10/29/09100%
    Fencing long Lead10/16/09100%
    Gate mfg. Long Lead0%
  Site Work plus08/28/09100%
    Secure Permits08/28/09100%
    Build up House Pad08/18/09100%
    compaction test08/18/09100%
    Set Forms08/21/09100%
    Rough-in underground plumbing, sewer & other08/25/09100%
    Install temporary power service08/24/09100%
    1.3 Inspect Plumbing Under/temp pwr08/26/09100%
    Backfill Plumbing08/27/09100%
  Foundation09/16/09100%
    Final Excavate & Prep for foundations08/28/09100%
    INSTALL POST TENSION CABLES08/31/09100%
    1.4 Inspection on Footings09/01/09100%
    Termite Pre-treat09/02/09100%
    Pour concrete for foundations & slabs09/03/09100%
    Strip foundation forms, GRADE & CURE09/04/09100%
    TENSION CABLES09/16/09100%
  Framing09/17/09100%
    Snap Lines stand walls09/08/09100%
    Plumb in Line - 1st Floor09/09/09100%
    roof framing (trusses & Sheeting)09/11/09100%
    complete interior framing09/16/09100%
    INSPECTION ROOF/SHEAR NAILING09/16/09100%
    Install Windows09/17/09100%
  Utility Rough-Ins09/18/09100%
    HVAC Calcs & layout09/14/09100%
    Rough-in HVAC09/16/09100%
    Rough-in gas plumb09/16/09100%
    Rough-in Plumbing09/17/09100%
    Rough-in electrical09/17/09100%
    Rough-in phone, cable09/18/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.09/22/09100%
  Dry In09/24/09100%
    Install felt, flashing,HOT MOP09/18/09100%
    Load Roof Tile09/24/09100%
  STUCCO &LATH09/29/09100%
    Complete Lathing09/22/09100%
    1.9.2 Inspect Drywall/lathing09/29/09100%
  Interior Finishes10/29/09100%
    Insulation09/22/09100%
      Place wall insulation09/22/09100%
      Place ceiling insulation09/22/09100%
    Drywall10/02/09100%
      Install drywall - 1st floor overhead09/28/09100%
      1.9.2 Inspect Drywall/lathing09/29/09100%
      Tape and float 1st floor drywall10/01/09100%
      Texture - and clean up10/02/09100%
    Trim Carpentry10/13/09100%
      install front door10/07/09100%
      DOORS,BASE,SHELVING10/13/09100%
    Paint 10/09/09100%
      Exterior Trim Paint10/05/09100%
      prep &Paint10/09/09100%
    Cabinets & woodwork10/19/09100%
      Cabinet Bases 10/13/09100%
      Cabinet Subtops & Scribe mold & uppers10/16/09100%
      base in fil/front lock10/19/09100%
    Countertops10/20/09100%
      Install formica Countertops10/20/09100%
     Tile installation10/29/09100%
      floor tile install10/22/09100%
      Grouting10/14/09100%
      Fix Grout10/29/09100%
  EXTERIOR FINISHES11/18/0978.08%
    Complete brown coat10/02/09100%
    Rough Grade10/06/09100%
    install cultured stone10/07/09100%
    Pour concrete driveway and sidewalks10/14/09100%
    Color Coat exterior10/26/09100%
    Install Roof Tile 10/28/09100%
    Install garage door10/26/09100%
    Install fence10/23/09100%
    INSTALL GATE10/26/09100%
    landscaping11/18/0920%
  FINAL TRIMS11/10/0983.53%
    Finish Electrical10/27/09100%
      Complete 1st floor circuits to service panel10/22/09100%
      Finalize Electrical10/27/09100%
    Install Light Fixtures (In & Out)10/29/09100%
    communications TRIM - phone, cable10/28/09100%
    Finish HVAC10/29/09100%
      Complete 1st floor - zone 1 HVAC10/28/09100%
      start check hvac10/29/09100%
    Final Trim11/10/0953.85%
      locks,stops screens,etc.appliances,etc.0%
      deliver appliances11/09/09100%
      Install Stove, Dishwaster, etc11/10/09100%
    Finish Plumbing10/28/09100%
       Install bath Fixtures10/28/09100%
     mirrors SHWR DOOR10/19/09100%
    Carpet0%
      Carpet 1st floor0%
  1.12 Complete final inspection for certificate of occupancy11/19/09100%
  Final Acceptance0%
    Cleanup for occupancy0%
    TOUCH UP PAINT0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule11/20/0969.81%
    Set up Loan08/17/09100%
    Draw #1 - 20%09/07/09100%
    Draw #2 - 25%09/18/09100%
    Draw #3 - 25%09/22/09100%
    Draw #4 - 20%10/12/09100%
    Draw #5 - 10%11/20/09100%
    owner for closing0%