Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:LR1 L95 P-1609
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
14order appliances 10/14/092w12/07/0972.75%
28Rough-in underground plumbing, sewer & other09/02/090h09/03/090%
31Backfill Plumbing09/04/090h09/04/090%
100Install Roof Tile 12/01/094d12/08/0950%
Task(s) Scheduled to Start in Between 12/02/09and12/18/09
99Color Coat exterior12/03/0916h12/04/090%
121 mirrors SHWR DOOR12/04/093d12/08/090%
102Install fence12/07/0948h12/14/090%
108Finalize Electrical12/07/098h12/07/090%
109Install Light Fixtures (In & Out)12/07/093d12/09/090%
112Complete 1st floor - zone 1 HVAC12/07/098h12/07/090%
116deliver appliances12/07/093h12/08/090%
110communications TRIM - phone, cable12/08/098h12/08/090%
113start check hvac12/08/092h12/08/090%
117Install Stove, Dishwaster, etc12/08/094h12/08/090%
1241.12 Complete final inspection for certificate of occupancy12/10/091d12/10/090%
104landscaping12/11/093d12/15/090%
126Cleanup for occupancy12/11/098h12/11/090%
136Draw #5 - 10%12/11/090.5h12/11/090%
127TOUCH UP PAINT12/14/091d12/14/090%
22Gate mfg. Long Lead12/15/0916h12/16/090%
103INSTALL GATE12/15/092d12/16/090%
All TasksFinished DatePercent Completed
3851 w 37th pl- Deanda12/02/0985.8%
  Sign contract08/31/09100%
  Color Chart Completed (Notice to Proceed)08/31/09100%
  Long Lead Items12/02/0992.85%
    power meter long lead09/07/09100%
    Temporary Power /BLUE STAKE09/03/09100%
    roof tile (LIVINGSTON) #10/12/09100%
    FRNT DR.10/19/09100%
    prefab wall mfg. PLAN-1609 W/ PATIO09/14/09100%
    post tension notification PLAN-160909/08/09100%
    Truss mfg.PLAN-160909/14/09100%
    Windows mfg. WHITE NO GRIDSLOW E09/18/09100%
    order appliances 12/02/0972.75%
     Cabinet Long Lead & Construction10/28/09100%
     1 marble countertop (mfg) long lead/ formica kit11/24/09100%
    order granite slab11/12/09100%
    order VANITY/shower Tile (see specs)11/20/09100%
    order Floor Tile 11/03/09100%
     order Carpet 11/27/09100%
    Fencing long Lead11/19/09100%
    Gate mfg. Long Lead0%
  Site Work plus09/04/09100%
    Secure Permits09/02/09100%
    Build up House Pad09/02/09100%
    compaction test09/02/09100%
    Set Forms09/01/09100%
    Rough-in underground plumbing, sewer & other09/03/090%
    Install temporary power service09/03/09100%
    1.3 Inspect Plumbing Under/temp pwr09/03/09100%
    Backfill Plumbing09/04/090%
  Foundation09/30/09100%
    Final Excavate & Prep for foundations09/07/09100%
    INSTALL POST TENSION CABLES09/14/09100%
    1.4 Inspection on Footings09/15/09100%
    Termite Pre-treat09/16/09100%
    Pour concrete for foundations & slabs09/17/09100%
    Strip foundation forms, GRADE & CURE09/18/09100%
    TENSION CABLES09/30/09100%
  Framing10/05/09100%
    Snap Lines stand walls09/24/09100%
    Plumb in Line - 1st Floor09/25/09100%
    roof framing (trusses & Sheeting)09/29/09100%
    complete interior framing10/02/09100%
    INSPECTION ROOF/SHEAR NAILING10/05/09100%
    Install Windows10/05/09100%
  Utility Rough-Ins10/08/09100%
    HVAC Calcs & layout10/05/09100%
    Rough-in HVAC10/06/09100%
    Rough-in gas plumb10/07/09100%
    Rough-in Plumbing10/06/09100%
    Rough-in electrical10/07/09100%
    Rough-in phone, cable10/08/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.10/08/09100%
  Dry In10/14/09100%
    Install felt, flashing,HOT MOP10/07/09100%
    Load Roof Tile10/14/09100%
  STUCCO &LATH10/14/09100%
    Complete Lathing10/09/09100%
    1.9.2 Inspect Drywall/lathing10/14/09100%
  Interior Finishes12/02/09100%
    Insulation10/09/09100%
      Place wall insulation10/09/09100%
      Place ceiling insulation10/09/09100%
    Drywall10/22/09100%
      Install drywall - 1st floor overhead10/13/09100%
      1.9.2 Inspect Drywall/lathing10/14/09100%
      Tape and float 1st floor drywall10/20/09100%
      Texture - and clean up10/22/09100%
    Trim Carpentry11/12/09100%
      install front door11/05/09100%
      DOORS,BASE,SHELVING11/12/09100%
    Paint 11/16/09100%
      Exterior Trim Paint11/16/09100%
      prep &Paint11/16/09100%
    Cabinets & woodwork11/20/09100%
      Cabinet Bases 11/18/09100%
      Cabinet Subtops & Scribe mold & uppers11/20/09100%
      base in fil/front lock11/20/09100%
    Countertops12/01/09100%
      Templates for Stone Tops 12/01/09100%
      Install Stone Countertop11/24/09100%
      Install formica Countertops11/24/09100%
      install marble top 11/24/09100%
     Tile installation12/02/09100%
      tile mstr vanity11/24/09100%
      tile backsplash in kit11/26/09100%
      floor tile install11/20/09100%
      Other first floor tile/ mstr bath floor11/23/09100%
      Grouting11/27/09100%
      Fix Grout12/02/09100%
  EXTERIOR FINISHES12/02/0960%
    Complete brown coat10/21/09100%
    Rough Grade10/23/09100%
    install cultured stone11/09/09100%
    Pour concrete driveway and sidewalks10/29/09100%
    Color Coat exterior0%
    Install Roof Tile 12/02/0950%
    Install garage door12/01/09100%
    Install fence0%
    INSTALL GATE0%
    landscaping0%
  FINAL TRIMS12/02/0954.29%
    Finish Electrical11/24/0966.67%
      Complete 1st floor circuits to service panel11/24/09100%
      Finalize Electrical0%
    Install Light Fixtures (In & Out)0%
    communications TRIM - phone, cable0%
    Finish HVAC0%
      Complete 1st floor - zone 1 HVAC0%
      start check hvac0%
    Final Trim08/31/0946.15%
      locks,stops screens,etc.appliances,etc.08/31/09100%
      deliver appliances0%
      Install Stove, Dishwaster, etc0%
    Finish Plumbing12/01/09100%
      Install bath Fixtures12/01/09100%
    RO AND SOFTNER12/02/09100%
     mirrors SHWR DOOR0%
  1.12 Complete final inspection for certificate of occupancy0%
  Final Acceptance0%
    Cleanup for occupancy0%
    TOUCH UP PAINT0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule11/16/0992.31%
    Set up Loan09/01/09100%
    Draw #1 - 20%09/21/09100%
    Draw #2 - 25%10/07/09100%
    Draw #3 - 25%10/09/09100%
    Draw #4 - 20%11/16/09100%
    Draw #5 - 10%0%
    Closing0%