| Project: | LR1 L27 P-3037 C |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 13 | order appliances CUSTOM | 10/08/09 | 2w | 12/07/09 | 72.25% |
| 15 | 1 marble countertop (mfg) long lead/ formica kit | 11/25/09 | 2w | 12/09/09 | 52.25% |
| 19 | order Carpet | 11/30/09 | 1w | 12/04/09 | 60% |
| 80 | Templates for Stone Tops | 11/25/09 | 1.5w | 12/07/09 | 69.67% |
| 96 | Install Roof Tile | 11/20/09 | 10d | 12/03/09 | 90% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 12/18/09 | |
| 81 | Install GRANITE BATH AND KIT JUPARANA ST CECEILIA | 12/07/09 | 8h | 12/08/09 | 0% |
| 100 | landscaping | 12/07/09 | 5d | 12/16/09 | 0% |
| 115 | Install bath Fixtures | 12/07/09 | 1d | 12/07/09 | 0% |
| 119 | Carpet 1st floor | 12/07/09 | 8h | 12/07/09 | 0% |
| 89 | Grouting | 12/08/09 | 8h | 12/09/09 | 0% |
| 90 | Fix Grout | 12/08/09 | 1h | 12/08/09 | 0% |
| 111 | locks,stops screens,etc.appliances,etc. | 12/08/09 | 6h | 12/08/09 | 0% |
| 116 | RO AND SOFTNER | 12/08/09 | 1d | 12/08/09 | 0% |
| 120 | 1.12 Complete final inspection for certificate of occupancy | 12/08/09 | 1d | 12/09/09 | 0% |
| 82 | Install formica Countertops | 12/09/09 | 8h | 12/10/09 | 0% |
| 83 | install marble top | 12/09/09 | 3h | 12/10/09 | 0% |
| 117 | mirrors CHM OBS SHWR DOOR | 12/09/09 | 3d | 12/14/09 | 0% |
| 132 | Draw #5 - 10% | 12/09/09 | 0.5h | 12/09/09 | 0% |
| 21 | Gate mfg. Long Lead | 12/14/09 | 16h | 12/16/09 | 0% |
| 122 | Cleanup for occupancy | 12/14/09 | 8h | 12/15/09 | 0% |
| 123 | TOUCH UP PAINT | 12/15/09 | 1d | 12/16/09 | 0% |
|
| All Tasks | Finished Date | Percent Completed |
| 3633 W 39TH ST OLIVERA/TRUJILLO | 12/02/09 | 90.46% |
| Sign contract | 06/18/09 | 100% |
| Color Chart Completed (Notice to Proceed) | 06/18/09 | 100% |
| Long Lead Items | 12/02/09 | 92.52% |
| power meter long lead | 06/25/09 | 100% |
| Temporary Power /BLUE STAKE | 06/23/09 | 100% |
| roof tile (LIVINGSTON) #3578 S TILE | 07/30/09 | 100% |
| FRNT DR. | 08/06/09 | 100% |
| prefab wall mfg. PLAN-3037 | 07/02/09 | 100% |
| post tension notification PLAN-3037 | 06/26/09 | 100% |
| Truss mfg.PLAN-3037 | 07/02/09 | 100% |
| Windows mfg. BIEGE LOW E GRIDS CLR | 07/08/09 | 100% |
| order appliances CUSTOM | 12/02/09 | 72.25% |
| Cabinet Long Lead & Construction | 10/06/09 | 100% |
| 1 marble countertop (mfg) long lead/ formica kit | 12/02/09 | 52.25% |
| order granite slab JUPARANA ST CECEILIA | 11/25/09 | 100% |
| order VANITY/shower Tile (see specs) | 07/02/09 | 100% |
| order Floor Tile | 10/22/09 | 100% |
| order Carpet | 12/02/09 | 60% |
| Fencing long Lead | 11/19/09 | 100% |
| Gate mfg. Long Lead | | 0% |
| Site Work plus | 06/30/09 | 100% |
| Secure Permits | 06/22/09 | 100% |
| Build up House Pad | 06/22/09 | 100% |
| compaction test | 06/22/09 | 100% |
| Set Forms | 06/23/09 | 100% |
| Rough-in underground plumbing, sewer & other | 06/26/09 | 100% |
| Install temporary power service | 06/24/09 | 100% |
| 1.3 Inspect Plumbing Under/temp pwr | 06/29/09 | 100% |
| Backfill Plumbing | 06/30/09 | 100% |
| Foundation | 07/22/09 | 100% |
| Final Excavate & Prep for foundations | 07/02/09 | 100% |
| INSTALL POST TENSION CABLES | 07/06/09 | 100% |
| 1.4 Inspection on Footings | 07/07/09 | 100% |
| Termite Pre-treat | 07/08/09 | 100% |
| Pour concrete for foundations & slabs | 07/09/09 | 100% |
| Strip foundation forms, GRADE & CURE | 07/10/09 | 100% |
| TENSION CABLES | 07/22/09 | 100% |
| Framing | 08/04/09 | 100% |
| Snap Lines stand walls | 07/14/09 | 100% |
| Plumb in Line - 1st Floor | 07/15/09 | 100% |
| roof framing (trusses & Sheeting) | 07/20/09 | 100% |
| complete interior framing | 08/03/09 | 100% |
| INSPECTION ROOF/SHEAR NAILING | 08/04/09 | 100% |
| Install Windows | 08/04/09 | 100% |
| Utility Rough-Ins | 08/21/09 | 100% |
| HVAC Calcs & layout | 08/03/09 | 100% |
| Rough-in HVAC | 08/05/09 | 100% |
| Rough-in gas plumb | 08/21/09 | 100% |
| Rough-in Plumbing | 08/21/09 | 100% |
| Rough-in electrical | 08/14/09 | 100% |
| Rough-in phone, cable | 08/17/09 | 100% |
| 1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc. | 08/27/09 | 100% |
| Dry In | 08/31/09 | 100% |
| Install felt, flashing,HOT MOP | 08/24/09 | 100% |
| Load Roof Tile | 08/31/09 | 100% |
| STUCCO &LATH | 09/22/09 | 100% |
| Complete Lathing | 09/04/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 09/22/09 | 100% |
| Interior Finishes | 12/02/09 | 88.81% |
| Insulation | 09/09/09 | 100% |
| Place wall insulation R-21 | 09/08/09 | 100% |
| Place ceiling insulation R-38 | 09/09/09 | 100% |
| Drywall | 10/08/09 | 100% |
| Install drywall - 1st floor overhead | 09/21/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 09/22/09 | 100% |
| Tape and float 1st floor drywall | 09/28/09 | 100% |
| Texture - and clean up | 10/08/09 | 100% |
| Trim Carpentry | 10/23/09 | 100% |
| install front door | 10/13/09 | 100% |
| DOORS,BASE,SHELVING | 10/23/09 | 100% |
| Paint | 10/30/09 | 100% |
| Exterior Trim Paint | 10/29/09 | 100% |
| prep &Paint | 10/30/09 | 100% |
| Cabinets & woodwork | 11/26/09 | 100% |
| Cabinet Bases | 11/17/09 | 100% |
| Cabinet Subtops & Scribe mold & uppers | 11/25/09 | 100% |
| base in fil/front lock | 11/26/09 | 100% |
| Countertops | 12/02/09 | 55% |
| Templates for Stone Tops | 12/02/09 | 69.67% |
| Install GRANITE BATH AND KIT JUPARANA ST CECEILIA | | 0% |
| Install formica Countertops | | 0% |
| install marble top | | 0% |
| Tile installation | 12/02/09 | 89.63% |
| WALK IN shower | 12/02/09 | 100% |
| TILE GARDEN TUB | 11/17/09 | 100% |
| floor tile install | 11/19/09 | 100% |
| Other first floor tile/ mstr bath floor | 11/23/09 | 100% |
| Grouting | | 0% |
| Fix Grout | | 0% |
| EXTERIOR FINISHES | 12/02/09 | 79.31% |
| Complete brown coat | 09/30/09 | 100% |
| Rough Grade | 10/01/09 | 100% |
| Pour concrete driveway and sidewalks | 10/20/09 | 100% |
| Color Coat exterior X-63149 HATTERAS | 11/19/09 | 100% |
| Install Roof Tile | 12/02/09 | 90% |
| Install garage door | 11/20/09 | 100% |
| Install fence | 12/01/09 | 100% |
| INSTALL GATE | 12/02/09 | 50% |
| landscaping | | 0% |
| FINAL TRIMS | 12/02/09 | 50% |
| Finish Electrical | 11/30/09 | 100% |
| Complete 1st floor circuits to service panel | 11/27/09 | 100% |
| Finalize Electrical | 11/30/09 | 100% |
| Install Light Fixtures (In & Out) | 12/02/09 | 100% |
| communications TRIM - phone, cable | 12/01/09 | 100% |
| Finish HVAC | 12/01/09 | 100% |
| Complete 1st floor - zone 1 HVAC | 11/30/09 | 100% |
| start check hvac | 12/01/09 | 100% |
| Final Trim | 12/02/09 | 40% |
| locks,stops screens,etc.appliances,etc. | | 0% |
| deliver appliances | 12/02/09 | 100% |
| Install Stove, Dishwaster, etc | 12/02/09 | 100% |
| Finish Plumbing | | 0% |
| Install bath Fixtures | | 0% |
| RO AND SOFTNER | | 0% |
| mirrors CHM OBS SHWR DOOR | | 0% |
| Carpet | | 0% |
| Carpet 1st floor | | 0% |
| 1.12 Complete final inspection for certificate of occupancy | | 0% |
| Final Acceptance | | 0% |
| Cleanup for occupancy | | 0% |
| TOUCH UP PAINT | | 0% |
| Perform final walk-through inspection | | 0% |
| Complete punch list items | | 0% |
| Loan & Draw Schedule | 11/02/09 | 26.09% |
| Set up Loan | 06/18/09 | 100% |
| Draw #1 - 20% | 07/08/09 | 100% |
| Draw #2 - 25% | 07/21/09 | 100% |
| Draw #3 - 25% | 08/28/09 | 100% |
| Draw #4 - 20% | 11/02/09 | 100% |
| Draw #5 - 10% | | 0% |
| Closing | | 0% |