Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:LR1 L27 P-3037 C
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
13order appliances CUSTOM10/08/092w12/07/0972.25%
15 1 marble countertop (mfg) long lead/ formica kit11/25/092w12/09/0952.25%
19 order Carpet 11/30/091w12/04/0960%
80Templates for Stone Tops 11/25/091.5w12/07/0969.67%
96Install Roof Tile 11/20/0910d12/03/0990%
Task(s) Scheduled to Start in Between 12/02/09and12/18/09
81Install GRANITE BATH AND KIT JUPARANA ST CECEILIA12/07/098h12/08/090%
100landscaping12/07/095d12/16/090%
115 Install bath Fixtures12/07/091d12/07/090%
119Carpet 1st floor12/07/098h12/07/090%
89Grouting12/08/098h12/09/090%
90Fix Grout12/08/091h12/08/090%
111locks,stops screens,etc.appliances,etc.12/08/096h12/08/090%
116RO AND SOFTNER12/08/091d12/08/090%
1201.12 Complete final inspection for certificate of occupancy12/08/091d12/09/090%
82Install formica Countertops12/09/098h12/10/090%
83install marble top 12/09/093h12/10/090%
117 mirrors CHM OBS SHWR DOOR12/09/093d12/14/090%
132Draw #5 - 10%12/09/090.5h12/09/090%
21Gate mfg. Long Lead12/14/0916h12/16/090%
122Cleanup for occupancy12/14/098h12/15/090%
123TOUCH UP PAINT12/15/091d12/16/090%
All TasksFinished DatePercent Completed
3633 W 39TH ST OLIVERA/TRUJILLO12/02/0990.46%
  Sign contract06/18/09100%
  Color Chart Completed (Notice to Proceed)06/18/09100%
  Long Lead Items12/02/0992.52%
    power meter long lead06/25/09100%
    Temporary Power /BLUE STAKE06/23/09100%
    roof tile (LIVINGSTON) #3578 S TILE07/30/09100%
    FRNT DR.08/06/09100%
    prefab wall mfg. PLAN-303707/02/09100%
    post tension notification PLAN-303706/26/09100%
    Truss mfg.PLAN-303707/02/09100%
    Windows mfg. BIEGE LOW E GRIDS CLR07/08/09100%
    order appliances CUSTOM12/02/0972.25%
     Cabinet Long Lead & Construction10/06/09100%
     1 marble countertop (mfg) long lead/ formica kit12/02/0952.25%
    order granite slab JUPARANA ST CECEILIA11/25/09100%
    order VANITY/shower Tile (see specs)07/02/09100%
    order Floor Tile 10/22/09100%
     order Carpet 12/02/0960%
    Fencing long Lead11/19/09100%
    Gate mfg. Long Lead0%
  Site Work plus06/30/09100%
    Secure Permits06/22/09100%
    Build up House Pad06/22/09100%
    compaction test06/22/09100%
    Set Forms06/23/09100%
    Rough-in underground plumbing, sewer & other06/26/09100%
    Install temporary power service06/24/09100%
    1.3 Inspect Plumbing Under/temp pwr06/29/09100%
    Backfill Plumbing06/30/09100%
  Foundation07/22/09100%
    Final Excavate & Prep for foundations07/02/09100%
    INSTALL POST TENSION CABLES07/06/09100%
    1.4 Inspection on Footings07/07/09100%
    Termite Pre-treat07/08/09100%
    Pour concrete for foundations & slabs07/09/09100%
    Strip foundation forms, GRADE & CURE07/10/09100%
    TENSION CABLES07/22/09100%
  Framing08/04/09100%
    Snap Lines stand walls07/14/09100%
    Plumb in Line - 1st Floor07/15/09100%
    roof framing (trusses & Sheeting)07/20/09100%
    complete interior framing08/03/09100%
    INSPECTION ROOF/SHEAR NAILING08/04/09100%
    Install Windows08/04/09100%
  Utility Rough-Ins08/21/09100%
    HVAC Calcs & layout08/03/09100%
    Rough-in HVAC08/05/09100%
    Rough-in gas plumb08/21/09100%
    Rough-in Plumbing08/21/09100%
    Rough-in electrical08/14/09100%
    Rough-in phone, cable08/17/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.08/27/09100%
  Dry In08/31/09100%
    Install felt, flashing,HOT MOP08/24/09100%
    Load Roof Tile08/31/09100%
  STUCCO &LATH09/22/09100%
    Complete Lathing09/04/09100%
    1.9.2 Inspect Drywall/lathing09/22/09100%
  Interior Finishes12/02/0988.81%
    Insulation09/09/09100%
      Place wall insulation R-2109/08/09100%
      Place ceiling insulation R-3809/09/09100%
    Drywall10/08/09100%
      Install drywall - 1st floor overhead09/21/09100%
      1.9.2 Inspect Drywall/lathing09/22/09100%
      Tape and float 1st floor drywall09/28/09100%
      Texture - and clean up10/08/09100%
    Trim Carpentry10/23/09100%
      install front door10/13/09100%
      DOORS,BASE,SHELVING10/23/09100%
    Paint 10/30/09100%
      Exterior Trim Paint10/29/09100%
      prep &Paint10/30/09100%
    Cabinets & woodwork11/26/09100%
      Cabinet Bases 11/17/09100%
      Cabinet Subtops & Scribe mold & uppers11/25/09100%
      base in fil/front lock11/26/09100%
    Countertops12/02/0955%
      Templates for Stone Tops 12/02/0969.67%
      Install GRANITE BATH AND KIT JUPARANA ST CECEILIA0%
      Install formica Countertops0%
      install marble top 0%
     Tile installation12/02/0989.63%
      WALK IN shower 12/02/09100%
      TILE GARDEN TUB11/17/09100%
      floor tile install11/19/09100%
      Other first floor tile/ mstr bath floor11/23/09100%
      Grouting0%
      Fix Grout0%
  EXTERIOR FINISHES12/02/0979.31%
    Complete brown coat09/30/09100%
    Rough Grade10/01/09100%
    Pour concrete driveway and sidewalks10/20/09100%
    Color Coat exterior X-63149 HATTERAS11/19/09100%
    Install Roof Tile 12/02/0990%
    Install garage door11/20/09100%
    Install fence12/01/09100%
    INSTALL GATE12/02/0950%
    landscaping0%
  FINAL TRIMS12/02/0950%
    Finish Electrical11/30/09100%
      Complete 1st floor circuits to service panel11/27/09100%
      Finalize Electrical11/30/09100%
    Install Light Fixtures (In & Out)12/02/09100%
    communications TRIM - phone, cable12/01/09100%
    Finish HVAC12/01/09100%
      Complete 1st floor - zone 1 HVAC11/30/09100%
      start check hvac12/01/09100%
    Final Trim12/02/0940%
      locks,stops screens,etc.appliances,etc.0%
      deliver appliances12/02/09100%
      Install Stove, Dishwaster, etc12/02/09100%
    Finish Plumbing0%
       Install bath Fixtures0%
    RO AND SOFTNER0%
     mirrors CHM OBS SHWR DOOR0%
    Carpet0%
      Carpet 1st floor0%
  1.12 Complete final inspection for certificate of occupancy0%
  Final Acceptance0%
    Cleanup for occupancy0%
    TOUCH UP PAINT0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule11/02/0926.09%
    Set up Loan06/18/09100%
    Draw #1 - 20%07/08/09100%
    Draw #2 - 25%07/21/09100%
    Draw #3 - 25%08/28/09100%
    Draw #4 - 20%11/02/09100%
    Draw #5 - 10%0%
    Closing0%