| Project: | SM1 L17 P-1500 |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 12 | order appliances std bisque | 11/30/09 | 2w | 12/11/09 | 30% |
| 14 | 1 marble countertop (mfg) 1 wilsonart 4551-01 blackstar granite | 11/20/09 | 2w | 12/03/09 | 90% |
| 91 | Standard (Tile entry, kitchen, utility room and baths) | 12/01/09 | 4.5d | 12/07/09 | 44.44% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 01/11/10 | |
| 89 | install marble top and formica | 12/04/09 | 3h | 12/04/09 | 0% |
| 92 | Other first floor tile (bath floors) | 12/07/09 | 3.5d | 12/10/09 | 0% |
| 99 | Color Coat exterior x-580 sierra tan | 12/07/09 | 16h | 12/08/09 | 0% |
| 100 | Install Roof Tile | 12/09/09 | 2d | 12/10/09 | 0% |
| 101 | Install 2 garage doors taupe 1 opener | 12/09/09 | 1d | 12/09/09 | 0% |
| 102 | Install fence | 12/09/09 | 32h | 12/14/09 | 0% |
| 112 | Complete 1st floor - zone 1 HVAC | 12/09/09 | 8h | 12/09/09 | 0% |
| 93 | Grouting | 12/11/09 | 8h | 12/11/09 | 0% |
| 109 | Install Light Fixtures (In & Out) | 12/11/09 | 3d | 12/16/09 | 0% |
| 108 | Finalize Electrical | 12/14/09 | 8h | 12/15/09 | 0% |
| 116 | deliver appliances | 12/14/09 | 3h | 12/14/09 | 0% |
| 117 | Install Stove, Dishwaster, etc | 12/14/09 | 4h | 12/15/09 | 0% |
| 20 | Gate mfg. Long Lead | 12/15/09 | 16h | 12/16/09 | 0% |
| 110 | communications TRIM - phone, cable | 12/15/09 | 8h | 12/16/09 | 0% |
| 119 | Install all Plumbing Fixtures | 12/15/09 | 8h | 12/16/09 | 0% |
|
| All Tasks | Finished Date | Percent Completed |
| 7954 E 37TH ST SPEC PLAN 1500 | 09/07/09 | 31.66% |
| Sign contract | 08/20/09 | 100% |
| Color Chart Completed (Notice to Proceed) | 08/20/09 | 100% |
| Long Lead Items | 09/07/09 | 55.56% |
| water meter long lead | 08/25/09 | 100% |
| Temporary Power /BLUE STAKE | 08/25/09 | 100% |
| roof tile production # 3578 | 10/01/09 | 100% |
| frnt dr rocky mtn. 2 panel tp rl. arch w/5/4 plank panel | 10/08/09 | 100% |
| prefab wall/lumber mfg. PLAN 1500 | 09/07/09 | 100% |
| Truss mfg.PLAN 1500 | 09/07/09 | 100% |
| Windows mfg. biege low e no grids obs in hall bath | 09/07/09 | 100% |
| order appliances std bisque | 12/02/09 | 30% |
| MERILATT SPRING VALLEY ARCH MAPLE STN SABLE | 11/04/09 | 100% |
| 1 marble countertop (mfg) 1 wilsonart 4551-01 blackstar granite | 12/02/09 | 90% |
| order granite slab | 11/19/09 | 100% |
| order MB VANITY/kit splsh/1 shwr& TUBDECK Tile | 09/17/09 | 100% |
| order Floor Tile | 11/27/09 | 100% |
| order Carpet | 12/02/09 | 6.25% |
| Fencing long Lead | 11/26/09 | 100% |
| Gate mfg. Long Lead | | 0% |
| Site Work plus | 09/03/09 | 100% |
| Secure Permits | 09/03/09 | 100% |
| Build up House Pad | 08/25/09 | 100% |
| Set Forms | 08/26/09 | 100% |
| Rough-in underground plumbing, sewer & other | 08/27/09 | 100% |
| Install temporary power service | 08/27/09 | 100% |
| 1.3 Inspect Plumbing Under/temp pwr | 09/02/09 | 100% |
| Backfill Plumbing | 09/02/09 | 100% |
| Foundation | 09/17/09 | 100% |
| Final Excavate & Prep for foundations | 09/04/09 | 100% |
| COMPACTION TEST | 09/07/09 | 100% |
| INSTALL POST TENSION CABLES | 09/07/09 | 100% |
| 1.4 Inspection on Footings | 09/08/09 | 100% |
| Termite Pre-treat | 09/09/09 | 100% |
| Pour concrete house and patios | 09/09/09 | 100% |
| Strip foundation forms, GRADE & CURE | 09/10/09 | 100% |
| GRADE | 09/10/09 | 100% |
| TENSION CABLES | 09/17/09 | 100% |
| Framing | 09/24/09 | 100% |
| Deliverlumber snap lines | 09/11/09 | 100% |
| Snap Lines stand walls | 09/14/09 | 100% |
| Plumb in Line - 1st Floor | 09/15/09 | 100% |
| deliver trusses | 09/17/09 | 100% |
| Deliver Second Frame Lumber Package | 09/17/09 | 100% |
| Complete roof framing (trusses & Sheeting) | 09/22/09 | 100% |
| INSPECTION ROOF NAILING | 09/24/09 | 100% |
| rough clean up | 09/23/09 | 100% |
| complete interior framing | 09/23/09 | 100% |
| INSPECTION SHEAR NAILING | 09/24/09 | 100% |
| Install Windows | 09/23/09 | 100% |
| Utility Rough-Ins | 10/01/09 | 100% |
| HVAC Calcs & layout | 09/23/09 | 100% |
| Rough-in HVAC | 09/28/09 | 100% |
| Rough-in gas plumb | 09/29/09 | 100% |
| Rough-in Plumbing | 09/30/09 | 100% |
| Rough-in electrical | 09/30/09 | 100% |
| Rough-in phone, cable | 09/30/09 | 100% |
| rough clean up | 10/01/09 | 100% |
| 1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc. | 10/06/09 | 100% |
| Dry In | 10/07/09 | 100% |
| Install felt, flashing,HOT MOP | 10/05/09 | 100% |
| Load Roof Tile | 10/07/09 | 100% |
| STUCCO &LATH | 10/13/09 | 100% |
| Complete Lathing | 10/08/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 10/13/09 | 100% |
| Interior Finishes | 12/02/09 | 75.74% |
| Insulation | 10/08/09 | 100% |
| Place wall insulation r-19 in garage too | 10/08/09 | 100% |
| Place ceiling insulation r-30 in house | 10/08/09 | 100% |
| Drywall | 10/19/09 | 100% |
| Install drywall - 1st floor overhead | 10/13/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 10/13/09 | 100% |
| Tape and float 1st floor drywall | 10/19/09 | 100% |
| Texture - 1st floor/CLEAN UP | 10/19/09 | 100% |
| Trim Carpentry | 11/03/09 | 100% |
| install front door | 10/30/09 | 100% |
| DOORS,BASE,SHELVING | 11/03/09 | 100% |
| Paint | 11/11/09 | 100% |
| Exterior Trim Paint | 11/06/09 | 100% |
| prep &Paint | 11/11/09 | 100% |
| Cabinets & woodwork | 11/20/09 | 100% |
| Cabinet Bases | 11/18/09 | 100% |
| Cabinet Subtops & Scribe mold & uppers | 11/19/09 | 100% |
| base in fil & front door lock | 11/20/09 | 100% |
| Countertops | | 0% |
| install marble top and formica | | 0% |
| Tile installation | 12/02/09 | 21.92% |
| Standard (Tile entry, kitchen, utility room and baths) | 12/02/09 | 44.44% |
| Other first floor tile (bath floors) | | 0% |
| Grouting | | 0% |
| Fix Grout | | 0% |
| EXTERIOR FINISHES | 11/19/09 | 67.6% |
| Complete brown coat | 10/15/09 | 100% |
| Rough Grade | 11/19/09 | 100% |
| Pour concrete driveway and sidewalks | | 0% |
| Color Coat exterior x-580 sierra tan | | 0% |
| Install Roof Tile | | 0% |
| Install 2 garage doors taupe 1 opener | | 0% |
| Install fence | | 0% |
| Install Gate 1-10' | | 0% |
| landscaping | | 0% |
| FINAL TRIMS | 12/02/09 | 22.86% |
| Finish Electrical | 12/02/09 | 66.67% |
| Complete 1st floor circuits to service panel | 12/02/09 | 100% |
| Finalize Electrical | | 0% |
| Install Light Fixtures (In & Out) | | 0% |
| communications TRIM - phone, cable | | 0% |
| Finish HVAC | | 0% |
| Complete 1st floor - zone 1 HVAC | | 0% |
| start check hvac | | 0% |
| Final Trim | | 0% |
| locks,stops hanicap hardware.appliances | | 0% |
| deliver appliances | | 0% |
| Install Stove, Dishwaster, etc | | 0% |
| Finish Plumbing | | 0% |
| Install all Plumbing Fixtures | | 0% |
| chm clr Shower door and mirrors | | 0% |
| Carpet | | 0% |
| Carpet 1st floor | | 0% |
| 1.12 Complete final inspection for certificate of occupancy | | 0% |
| Final Acceptance | | 0% |
| Cleanup for occupancy | | 0% |
| TOUCH UP PAINT | | 0% |
| Perform final walk-through inspection | | 0% |
| Complete punch list items | | 0% |
| Loan & Draw Schedule | 11/12/09 | 66.67% |
| Set up Loan | 08/20/09 | 100% |
| Draw #1 - 20% | 09/21/09 | 100% |
| Draw #2 - 25% | 10/06/09 | 100% |
| Draw #3 - 25% | 10/29/09 | 100% |
| Draw #4 - 20% | 11/12/09 | 100% |
| Draw #5 - 10% | | 0% |
| Closing | | 0% |