Home | Customer Progress | Contractor Progress AboutHelp
Home > Customer Progress > Project Status > Last Updated: 12/02/09

Project:SM1 L17 P-1500
Schedule StartDurationSchedule FinishPercent Complete
Uncompleted Task(s) Scheduled before:12/02/09
12order appliances std bisque11/30/092w12/11/0930%
14 1 marble countertop (mfg) 1 wilsonart 4551-01 blackstar granite11/20/092w12/03/0990%
91Standard (Tile entry, kitchen, utility room and baths)12/01/094.5d12/07/0944.44%
Task(s) Scheduled to Start in Between 12/02/09and01/11/10
89install marble top and formica12/04/093h12/04/090%
92Other first floor tile (bath floors)12/07/093.5d12/10/090%
99Color Coat exterior x-580 sierra tan12/07/0916h12/08/090%
100Install Roof Tile12/09/092d12/10/090%
101Install 2 garage doors taupe 1 opener12/09/091d12/09/090%
102Install fence12/09/0932h12/14/090%
112Complete 1st floor - zone 1 HVAC12/09/098h12/09/090%
93Grouting12/11/098h12/11/090%
109Install Light Fixtures (In & Out)12/11/093d12/16/090%
108Finalize Electrical12/14/098h12/15/090%
116deliver appliances12/14/093h12/14/090%
117Install Stove, Dishwaster, etc12/14/094h12/15/090%
20Gate mfg. Long Lead12/15/0916h12/16/090%
110communications TRIM - phone, cable12/15/098h12/16/090%
119Install all Plumbing Fixtures12/15/098h12/16/090%
All TasksFinished DatePercent Completed
7954 E 37TH ST SPEC PLAN 150009/07/0931.66%
  Sign contract08/20/09100%
  Color Chart Completed (Notice to Proceed)08/20/09100%
  Long Lead Items09/07/0955.56%
    water meter long lead08/25/09100%
    Temporary Power /BLUE STAKE08/25/09100%
    roof tile production # 357810/01/09100%
    frnt dr rocky mtn. 2 panel tp rl. arch w/5/4 plank panel10/08/09100%
    prefab wall/lumber mfg. PLAN 150009/07/09100%
    Truss mfg.PLAN 150009/07/09100%
    Windows mfg. biege low e no grids obs in hall bath09/07/09100%
    order appliances std bisque12/02/0930%
    MERILATT SPRING VALLEY ARCH MAPLE STN SABLE11/04/09100%
     1 marble countertop (mfg) 1 wilsonart 4551-01 blackstar granite12/02/0990%
    order granite slab11/19/09100%
    order MB VANITY/kit splsh/1 shwr& TUBDECK Tile 09/17/09100%
    order Floor Tile 11/27/09100%
     order Carpet12/02/096.25%
    Fencing long Lead11/26/09100%
    Gate mfg. Long Lead0%
  Site Work plus09/03/09100%
    Secure Permits09/03/09100%
    Build up House Pad08/25/09100%
    Set Forms08/26/09100%
    Rough-in underground plumbing, sewer & other08/27/09100%
    Install temporary power service08/27/09100%
    1.3 Inspect Plumbing Under/temp pwr09/02/09100%
    Backfill Plumbing09/02/09100%
  Foundation09/17/09100%
    Final Excavate & Prep for foundations09/04/09100%
    COMPACTION TEST09/07/09100%
    INSTALL POST TENSION CABLES09/07/09100%
    1.4 Inspection on Footings09/08/09100%
    Termite Pre-treat09/09/09100%
    Pour concrete house and patios09/09/09100%
    Strip foundation forms, GRADE & CURE09/10/09100%
    GRADE09/10/09100%
    TENSION CABLES09/17/09100%
  Framing09/24/09100%
    Deliverlumber snap lines09/11/09100%
    Snap Lines stand walls09/14/09100%
    Plumb in Line - 1st Floor09/15/09100%
    deliver trusses09/17/09100%
    Deliver Second Frame Lumber Package09/17/09100%
    Complete roof framing (trusses & Sheeting)09/22/09100%
    INSPECTION ROOF NAILING09/24/09100%
    rough clean up09/23/09100%
    complete interior framing09/23/09100%
    INSPECTION SHEAR NAILING09/24/09100%
    Install Windows09/23/09100%
  Utility Rough-Ins10/01/09100%
    HVAC Calcs & layout09/23/09100%
    Rough-in HVAC09/28/09100%
    Rough-in gas plumb09/29/09100%
    Rough-in Plumbing09/30/09100%
    Rough-in electrical09/30/09100%
    Rough-in phone, cable09/30/09100%
    rough clean up10/01/09100%
  1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc.10/06/09100%
  Dry In10/07/09100%
    Install felt, flashing,HOT MOP10/05/09100%
    Load Roof Tile10/07/09100%
  STUCCO &LATH10/13/09100%
    Complete Lathing10/08/09100%
    1.9.2 Inspect Drywall/lathing10/13/09100%
  Interior Finishes12/02/0975.74%
    Insulation10/08/09100%
      Place wall insulation r-19 in garage too10/08/09100%
      Place ceiling insulation r-30 in house10/08/09100%
    Drywall10/19/09100%
      Install drywall - 1st floor overhead10/13/09100%
      1.9.2 Inspect Drywall/lathing10/13/09100%
      Tape and float 1st floor drywall10/19/09100%
      Texture - 1st floor/CLEAN UP10/19/09100%
    Trim Carpentry11/03/09100%
      install front door10/30/09100%
      DOORS,BASE,SHELVING11/03/09100%
    Paint 11/11/09100%
      Exterior Trim Paint11/06/09100%
      prep &Paint11/11/09100%
    Cabinets & woodwork11/20/09100%
      Cabinet Bases 11/18/09100%
      Cabinet Subtops & Scribe mold & uppers11/19/09100%
      base in fil & front door lock11/20/09100%
    Countertops0%
      install marble top and formica0%
     Tile installation12/02/0921.92%
      Standard (Tile entry, kitchen, utility room and baths)12/02/0944.44%
      Other first floor tile (bath floors)0%
      Grouting0%
      Fix Grout0%
  EXTERIOR FINISHES11/19/0967.6%
    Complete brown coat10/15/09100%
    Rough Grade11/19/09100%
    Pour concrete driveway and sidewalks0%
    Color Coat exterior x-580 sierra tan0%
    Install Roof Tile0%
    Install 2 garage doors taupe 1 opener0%
    Install fence0%
    Install Gate 1-10'0%
    landscaping0%
  FINAL TRIMS12/02/0922.86%
    Finish Electrical12/02/0966.67%
      Complete 1st floor circuits to service panel12/02/09100%
      Finalize Electrical0%
    Install Light Fixtures (In & Out)0%
    communications TRIM - phone, cable0%
    Finish HVAC0%
      Complete 1st floor - zone 1 HVAC0%
      start check hvac0%
    Final Trim0%
      locks,stops hanicap hardware.appliances0%
      deliver appliances0%
      Install Stove, Dishwaster, etc0%
    Finish Plumbing0%
      Install all Plumbing Fixtures0%
    chm clr Shower door and mirrors0%
    Carpet0%
      Carpet 1st floor0%
  1.12 Complete final inspection for certificate of occupancy0%
  Final Acceptance0%
    Cleanup for occupancy0%
    TOUCH UP PAINT0%
    Perform final walk-through inspection0%
    Complete punch list items0%
  Loan & Draw Schedule11/12/0966.67%
    Set up Loan08/20/09100%
    Draw #1 - 20%09/21/09100%
    Draw #2 - 25%10/06/09100%
    Draw #3 - 25%10/29/09100%
    Draw #4 - 20%11/12/09100%
    Draw #5 - 10%0%
    Closing0%