| Project: | LQ2 L96 PLAN 2 3-car ? |
| | Schedule Start | Duration | Schedule Finish | Percent Complete |
| Uncompleted Task(s) Scheduled before: | 12/02/09 | |
| 16 | order 3 showers tile | 07/02/09 | 2w | 01/04/10 | 50% |
|
| Task(s) Scheduled to Start in Between | 12/02/09 | and | 03/15/10 | |
|
| All Tasks | Finished Date | Percent Completed |
| 4594 W IRMA ST SPEC PLAN 2 3 CAR | 09/29/09 | 62.43% |
| Sign contract | 03/27/09 | 100% |
| Color Chart Completed (Notice to Proceed) | 03/27/09 | 100% |
| Long Lead Items | 07/30/09 | 62.22% |
| new owner | | 0% |
| order roof tile (la quinta) | 03/27/09 | 100% |
| Exterior Door Long Lead Time | 05/15/09 | 100% |
| post tension notification PLAN 2 3 CAR | 04/10/09 | 100% |
| prefab walls PLAN 2 3 CAR | 04/17/09 | 100% |
| Truss Long Lead time PLAN 2 3 CAR | 04/17/09 | 100% |
| order Windows | 04/16/09 | 100% |
| CONCRETE TRIM LONG LEAD TIME | 04/17/09 | 100% |
| order appliances CUSTOM | | 0% |
| order Cabinets | 07/30/09 | 100% |
| order 3 bathroom vanities tile | | 0% |
| order 3 showers tile | 07/17/09 | 50% |
| order Floor Tile Long Lead time | | 0% |
| stone countertop (mfg) long lead | | 0% |
| Carpet Long Lead Time | 04/10/09 | 100% |
| Fencing long Lead | 07/21/09 | 100% |
| Gate mfg. Long Lead | | 0% |
| Site Work plus | 04/16/09 | 100% |
| Secure Permits | 04/07/09 | 100% |
| Water Meter Installed | 03/27/09 | 100% |
| Build up House Pad | 03/31/09 | 100% |
| Set Forms | 04/06/09 | 100% |
| Install temporary power service | 04/07/09 | 100% |
| Rough-in underground plumbing, sewer & other | 04/14/09 | 100% |
| 1.3 Inspect Plumbing Under/temp pwr | 04/15/09 | 100% |
| Backfill Plumbing | 04/16/09 | 100% |
| Foundation | 05/01/09 | 100% |
| Underground Electrical / Islands | 04/17/09 | 100% |
| Final Excavate & Prep for foundations | 04/17/09 | 100% |
| post tension cables installed | 04/20/09 | 100% |
| 1.4 Inspection on Footings | 04/21/09 | 100% |
| Termite Pre-treat | 04/21/09 | 100% |
| Pour concrete for foundation and garage | 04/22/09 | 100% |
| Strip forms& CURE foundation | 04/24/09 | 100% |
| tension cables | 05/01/09 | 100% |
| Framing | 05/28/09 | 100% |
| Snap Lines | 04/24/09 | 100% |
| Deliver wall panels/lumber | 04/24/09 | 100% |
| deliver trusses | 04/28/09 | 100% |
| Frame 1st floor walls | 04/27/09 | 100% |
| Install 1st floor trusses | 05/04/09 | 100% |
| Complete roof framing (trusses & Sheeting) | 05/14/09 | 100% |
| INSPECTION ROOF NAILING | 05/15/09 | 100% |
| rough clean up | 05/15/09 | 100% |
| complete interior framing | 05/21/09 | 100% |
| INSPECTION SHEAR NAILING | 05/22/09 | 100% |
| Install Fireplace | 05/28/09 | 100% |
| Install Windows | 05/22/09 | 100% |
| Utility Rough-Ins | 06/15/09 | 100% |
| HVAC Calcs & layout | 05/26/09 | 100% |
| Rough-in HVAC | 05/28/09 | 100% |
| Rough-in gas plumb | 06/05/09 | 100% |
| Rough-in Plumbing | 06/05/09 | 100% |
| Rough-in electrical | 06/11/09 | 100% |
| Rough-in phone, cable | 06/12/09 | 100% |
| rough clean up | 06/15/09 | 100% |
| 1.6 Inspection -- Framing, Rough-in Elect, Plumbing HVAC, etc. | 06/16/09 | 100% |
| Dry In | 06/15/09 | 100% |
| Install felt, flashing,Hot mop | 06/12/09 | 100% |
| Load Roof Tile | 06/15/09 | 100% |
| LATHING | 07/07/09 | 100% |
| Complete Lathing | 06/19/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 07/07/09 | 100% |
| Interior Finishes | 09/28/09 | 40.41% |
| Insulation | 06/22/09 | 100% |
| Place wall insulation | 06/22/09 | 100% |
| Place ceiling insulation | 06/22/09 | 100% |
| Drywall | 07/10/09 | 100% |
| Install drywall | 07/06/09 | 100% |
| 1.9.2 Inspect Drywall/lathing | 07/06/09 | 100% |
| Tape and float drywall | 07/08/09 | 100% |
| Texture - 1st floor | 07/10/09 | 100% |
| Drywall Cleanup | 07/10/09 | 100% |
| Trim Carpentry | 09/25/09 | 100% |
| install front door Hang doors | 07/22/09 | 100% |
| Baseboards,CROWN, SHELVING | 09/25/09 | 100% |
| Paint | 09/28/09 | 100% |
| Exterior Trim Paint | 07/14/09 | 100% |
| prep and Paint | 09/28/09 | 100% |
| Cabinets & woodwork | | 0% |
| Cabinet Bases | | 0% |
| Cabinet Subtops & Scribe mold & uppers | | 0% |
| TEMPLATE FOR STONE | | 0% |
| INSTALL STONE TOPS | | 0% |
| Tile installation | | 0% |
| mud tops and shower | | 0% |
| snail shower | | 0% |
| walk in shower | | 0% |
| drop in tub deck | | 0% |
| tile mstr vanity | | 0% |
| tile 2nd vanity | | 0% |
| tile3rd vanity | | 0% |
| Fireplace Facing 1 | | 0% |
| Standard (Tile entry, kitchen, utility room and baths) | | 0% |
| Other first floor tile (bath floors) | | 0% |
| Grouting | | 0% |
| Fix Grout | | 0% |
| Exterior Finishes | 08/10/09 | 21.79% |
| Complete brown coat | 07/13/09 | 100% |
| Rough Grade | 07/24/09 | 100% |
| Pour concrete driveway and sidewalks | | 0% |
| INSTALL CONCRETE TRIM | 08/10/09 | 100% |
| Install COURTYARD fence | | 0% |
| Install garage door | | 0% |
| Color Coat exterior LA QUINTA | | 0% |
| Install Roof Tile | | 0% |
| Install Gate | | 0% |
| landscaping | | 0% |
| final trims | | 0% |
| Finish Electrical | | 0% |
| Complete 1st floor circuits to service panel | | 0% |
| Finalize Electrical | | 0% |
| Install Light Fixtures (In & Out) | | 0% |
| Complete communications wiring - phone, cable, computer, alarm | | 0% |
| Finish HVAC | | 0% |
| Complete 1st floor - zone 1 HVAC | | 0% |
| start check hvac | | 0% |
| Final Trim | | 0% |
| locks,stops screens,etc.appliances,etc. | | 0% |
| deliver appliances | | 0% |
| Install Stove, Dishwaster, etc | | 0% |
| Finish Plumbing | | 0% |
| Install all Plumbing Fixtures | | 0% |
| Shower doors and mirrors | | 0% |
| 1.12 Complete final inspection for certificate of occupancy | | 0% |
| Final Acceptance | | 0% |
| Cleanup for occupancy | | 0% |
| touch up paint and grout touch up | | 0% |
| Perform final walk-through inspection | | 0% |
| Complete punch list items | | 0% |
| Loan & Draw Schedule | 09/29/09 | 26.09% |
| Set up Loan | 03/27/09 | 100% |
| Draw #1 - 20% | 04/21/09 | 100% |
| Draw #2 - 25% | 05/15/09 | 100% |
| Draw #3 - 25% | 06/17/09 | 100% |
| Draw #4 - 20% | 09/29/09 | 100% |
| Draw #5 - 10% | | 0% |
| Closing | | 0% |